What types of models are included in the CM as Agency delivery system?

Prepare for the AGC BIM Construction Management Test. Study with our comprehensive quizzes, featuring flashcards and detailed explanations. Master BIM concepts and excel!

In the context of the CM as Agency delivery system, the inclusion of Design Model, Construction Model, and Project Model represents a comprehensive approach to managing a construction project.

The Design Model is focused on the initial architectural and engineering designs of the project, providing a visual and technical representation of how the finished structure will look and function. This model plays a crucial role in ensuring that all design elements are appropriately integrated and that the project adheres to the required regulations and standards.

The Construction Model is essential for actual construction activities, incorporating details such as sequencing, resource management, and logistics. This model helps in managing the workflow on-site and ensuring that the project is executed according to the designed plans, optimizing the efficiency of construction processes.

The Project Model encompasses the entire project lifecycle, including planning, design, and construction phases. It takes into account various dimensions of project management, such as time, cost, quality, and collaboration among stakeholders. By using a Project Model, the management team can facilitate communication, coordination, and decision-making, leading to better project outcomes.

In summary, by integrating the Design Model, Construction Model, and Project Model, the CM as Agency delivery system leverages a holistic view of the project, enhancing collaboration, efficiency, and ultimately contributing